will county board graphic

Commission Grants Green Garden Solar Farm Project Variance Extension

Spread the love

Will County Planning and Zoning Commission Meeting | November 4, 2025

Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial solar energy facility in Green Garden Township, allowing the developer to wait for optimal planting conditions in Spring 2026 before proceeding. The variances, originally approved in March, concern the mowing schedule and plant height for the native pollinator habitat required for the project.

Green Garden Solar Farm Key Points:

  • The first-time extension was granted for variances associated with a 35-acre solar project on LaGrange Road near West Manhattan-Monee Road.

  • The variances reduce the required number of mowings from five to one per year and increase the maximum allowed ground cover height from 13 to 36 inches.

  • The developer requested the extension to allow time to prepare the site for planting a native pollinator seed mix in favorable spring conditions.

A commercial solar energy facility planned for Green Garden Township received a procedural timeline extension from the Will County Planning and Zoning Commission on Tuesday, November 4, 2025.

The commission approved a 180-day extension for two variances previously granted to applicant TPE IL WI258, LLC, an affiliate of TPE Development, LLC, for a 35-acre solar farm. The project is located on vacant property at the northeast corner of LaGrange Road and West Manhattan-Monee Road in Monee.

The variances, originally approved by the commission on March 4, 2025, are key to the project’s use of native plantings and agrivoltaics—the simultaneous use of land for agriculture and solar power generation. One variance reduces the required number of mowings from five times per year to just one, while the other increases the maximum allowable plant height from 13 inches to 36 inches. These changes are necessary to establish and maintain a healthy native pollinator habitat on the site, which is a requirement of the state’s community solar program.

According to a memo from county staff, the developer has not yet applied for a building permit because “favorable planting conditions for the site are not expected until after the variances expire on March 4, 2026.” The extension was requested to allow the developer time to prepare the site for planting in the spring of 2026.

The commission, which is authorized to grant up to two 180-day extensions for good cause, approved the request. The variances will now expire on August 31, 2026.

Events

No events

Leave a Comment





Latest News Stories

Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...
new-lenox-fire-district-stations.3

New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community

NEW LENOX – The New Lenox Fire Protection District is adding a four-legged member to its team after the Board of Trustees unanimously approved the creation of a new comfort...
new-lenox-library.2-1

Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs

NEW LENOX – The New Lenox Public Library’s creative hub, The Studio, is experiencing a surge in popularity, shattering attendance records and successfully launching new technology-driven programs, according to a...
New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
Mokena Park District.logo.graphic.1

Mokena Park District Approves $550,000 Fund Transfer for Major Park Projects

The Mokena Community Park District Board of Commissioners has approved a $550,000 fund transfer to complete several key capital projects, including the construction of a new bathroom facility at Hecht...
LWSRA

Mokena Park District Joins Regional Partners in Renewed Funding Commitment for LWSRA

The Mokena Community Park District is renewing its financial commitment to the Lincolnway Special Recreation Association (LWSRA), joining eight other local park districts in an intergovernmental agreement that ensures continued...