diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Spread the love

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for Crawford, Murphy & Tilly, Inc. to update plans to account for several new commercial and residential developments along the corridor in New Lenox and Frankfort.

Laraway Road Project Key Points:

  • Funding: The board approved $468,374 from Motor Fuel Tax funds for supplemental design services.

  • Location: The project covers a four-mile stretch of Laraway Road (CH 74) from Cedar Road to Wolf Road.

  • Reason: Original plans needed significant updates to accommodate new developments, including Camelot Homes, a Gas N Wash, a fueling center, and the Homestead Commercial strip mall.

  • Scope: The overall project will widen Laraway Road from a two-lane rural road to a five-lane divided roadway.

NEW LENOX/FRANKFORT — The massive project to widen and reconstruct Laraway Road through New Lenox and Frankfort will require nearly half a million dollars in additional design work to accommodate a boom in local development. The Will County Board on Thursday approved a $468,374 supplemental professional services agreement with the engineering firm Crawford, Murphy & Tilly, Inc.

The funding is necessary to redesign portions of the four-mile project—stretching from Cedar Road to Wolf Road—to integrate new access points and adjust for new construction that has occurred since the initial plans were developed. The overall project will transform the two-lane rural road into a five-lane, urban-style roadway with a closed drainage system.

According to the project scope, design plans needed to be updated to account for six new developments, including Camelot Homes at Spencer Road, a Gas N Wash and a fueling center at Schoolhouse Road, and the Homestead Commercial strip mall at Wolf Road.

In addition to incorporating new access points and adjusting the road’s profile, the supplemental work includes redesigning the geometry of the Wolf Road intersection, adding a mill and overlay section at the project’s west end, designing traffic signal interconnects, and planning for watermain relocations. The board unanimously approved the expenditure, which will be covered by the county’s allotment of Motor Fuel Tax funds.

Events

No events

Leave a Comment





Latest News Stories

Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County’s Major Capital Projects Hit Key Milestones, VAC Buildout on “Aggressive Schedule”

Will County is making significant headway on several major capital improvement projects, with the new Veterans Assistance Commission (VAC) & Support Center in Joliet on an “aggressive schedule” for a...
Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

County Board Approves 2026-2031 Transportation Plan Despite Project Opposition

Will County board members approved a contested five-year transportation improvement plan Tuesday after heated debate over a controversial Homer Glen road project that has drawn sustained community opposition. The Will...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Contentious I-3 Rezoning for DuPage Township Storage Yard Narrowly Advances

A proposal to rezone a 20-acre parcel in DuPage Township from agricultural to the county's most intensive industrial classification narrowly earned a recommendation for approval from the Will County Planning...
Meeting-Briefs

Will County Legislative Committee July 1 Meeting Briefs

Federal Budget Impact: Will County could face significant funding challenges if federal budget reconciliation measures reduce Medicaid and SNAP benefits. The county health department and social services rely heavily on...
Will-County-Finance-Committee-Meeting-July-1-2025

County Moves Forward with $200.8 Million Bond Refinancing Plan

Will County Finance Committee members on July 1 approved moving forward with a comprehensive bond refinancing ordinance that could save taxpayers more than $716,000 over the life of the bonds...
Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...