Mokena 159 Board Approves Increased Cost for Junior High Storage Shed Amid Budget Debate

Spread the love

Mokena School District 159 Board of Education Meeting | October 15, 2025

Article Summary: The Mokena School District 159 Board of Education approved a cost increase for a new storage shed at Mokena Junior High School, raising the project’s total cost to a maximum of $176,000. The decision, which passed in a contentious 5-2 vote, sparked a debate over fiscal responsibility in light of the district’s budget deficit and the intent of referendum funds.

MJHS Storage Shed Project Key Points:

  • The board approved a revised project cost not to exceed $176,000, an increase from the previously approved $162,500.

  • The cost increase is due to a newly required perimeter frost footing for the shed’s foundation, a change from the original design.

  • The project is funded through the “Warm, Safe, and Dry” referendum funds, designated for facilities and maintenance.

  • Board members debated whether the expenditure was responsible given the district’s budget deficit and if the funds could be better used elsewhere.

MOKENA, IL — The Mokena School District 159 Board of Education on Wednesday, October 15, 2025, approved an increased budget for the Mokena Junior High School (MJHS) storage shed project, bringing the total cost to a maximum of $176,000. The vote followed a lengthy and pointed debate among board members about the project’s necessity, timing, and funding source amid a projected $1.3 million budget deficit.

The project, initially approved in September 2024 for $162,500, requires additional funding due to a change in construction requirements. According to a memo from Dr. Teri Shaw, the district’s Chief School Business Official, the shed’s provider now requires a perimeter frost footing instead of the previously planned thickened slab edge. This change necessitates deeper excavation and more concrete, increasing the cost for contractor Bear Construction by $14,600 to a total of $159,600. The total project cost is not to exceed $176,000.

Board member Kelli MacMillan voiced strong opposition to the project, calling it an “irresponsible spend.” She argued that the district is operating without the shed now and could delay the project indefinitely, particularly given the budget deficit.

“We are in a deficit, meaning we are spending $1.3 million… more than the revenue we have coming in,” MacMillan stated. “I don’t feel good about prioritizing a shed over students and staff. I don’t feel good about it and that’s why I won’t do it.”

MacMillan also questioned the use of referendum funds, which she said were intended to keep students “warm, safe and dry, not construction equipment.” She pointed out that the district is budgeting to transfer $190,000 from its working cash fund reserves to its Operations and Maintenance (O&M) fund. “Essentially, we’re saying we need money from our reserves to pay for a $176,000 shed that does not impact our classrooms. And I have an issue with that,” she said.

Board President Jim Andresen countered, stating that the funds for the shed come from the “Warm, Safe, and Dry” referendum, which are legally restricted for facilities, maintenance, and equipment protection. He stressed that this money could not be reallocated to classroom or salary expenses.

“This does not impact a classroom. The promise was made… to use that money for the facilities,” Andresen said. “This is not making the students do without. This is making sure we are protecting the capital investments we made with our equipment… We have to take care of our equipment and this is no different.”

Andresen added that a “forever lock” was placed on the referendum funds, requiring a unanimous board vote to ever use them for purposes outside of facilities, such as salaries or school supplies. “Please do not think for a second that that trust is going to be violated,” he said.

Board member Lisa Zielinski also expressed reservations but ultimately supported the project. “I struggle with the warm, safe, and dry and if it’s aesthetics,” she commented, before thanking the administration for bringing the cost increase to the board for a vote, even though the amount was within a 10% threshold that did not technically require re-approval.

The motion to approve the increased cost passed 5-2, with members MacMillan and Julie Oost voting against it.

Events

No events

Leave a Comment





Latest News Stories

Screenshot-2025-08-13-at-2.11.44-PM

Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance

Article Summary: The Monee Village Board has approved its annual appropriations ordinance, which acts as the village's legal spending authority for the fiscal year that began May 1, 2025. The...
New-Lenox-School-122.3

New Lenox School District 122 Honors State Track and Field Athletes

New Lenox School District 122 took time during its June 17 board meeting to celebrate the outstanding achievements of its junior high athletes at the 2025 IESA State Track and...

Fiber Optic Internet Competition Coming to New Lenox

NEW LENOX – Residents may soon have a new choice for high-speed internet, as Champaign-based Pavlov Media announced its intention to build out a fiber optic network across the village....
Screenshot-2025-08-13-at-2.15.28-PM

Monee Officials Issue Pool Safety Alert Amid Summer Heat

Article Summary: Following an increase in new pool installations, Monee's Building Services department is reminding residents of mandatory permit and safety requirements. Officials are emphasizing life-safety measures to prevent drownings,...
New-Lenox-Village-Board

Village Board Approves Millions in Spending on Roads, Parks, and Museum

NEW LENOX – The New Lenox Village Board authorized millions of dollars in spending on Monday for its annual road program and for continued investment in its newest community amenities,...
Meeting-Briefs

Meeting Summary: New Lenox School District 122 Board of Education for June 17, 2025

The New Lenox School District 122 Board of Education handled significant financial business at its June 17 meeting, approving a tentative budget for the 2025-2026 school year and renewing insurance...
Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 28, 2025

The New Lenox Village Board meeting on Monday was marked by ceremony and significant action on major developments. The board honored the new Pope Leo XIV and retiring Police Chief...
Meeting-Briefs

Meeting Summary and Briefs: Monee Village Board for July 23, 2025

The Monee Village Board of Trustees heard a detailed presentation for a major industrial redevelopment, approved a significant payment for its nearly-completed public works facility, and gave final clearance for...
frankfort township graphic.2

Frankfort Square Resident Asks Township to Allow Golf Carts on Streets

Article Summary: A Mokena resident has formally requested that the Frankfort Township Board create an ordinance to permit the use of golf carts on streets within the Frankfort Square subdivision. In...
Frankfort-Township-Logo-Graphic

Frankfort Township Board Adopts Annual Budgets for Township, Highway Departments

Article Summary: The Frankfort Township Board of Trustees formally approved its annual appropriation ordinances for the township and its highway department, setting the spending plan for all programs and obligations for...
new-lenox-fire-district-stations.2

New Lenox Fire Board Denies Variance Over Extreme Hydrant Distance, Citing Safety

NEW LENOX – The New Lenox Fire Protection District Board of Trustees unanimously denied a homeowner's variance request on Monday, citing significant public safety concerns over the property's extreme distance...
new-lenox-fire-district-stations.4

New Lenox Fire District Secures $35,000 Grant for UTV in Solar Farm Agreement

NEW LENOX – The New Lenox Fire Protection District is set to receive a $35,000 grant to purchase a new Utility Task Vehicle (UTV) as part of a community benefit...
Meeting-Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Mokena Park District.logo.graphic.1

Mokena Park District Approves $7.9 Million Budget, Eyes Major Park Upgrades

The Mokena Community Park District Board of Commissioners has tentatively approved a $7.9 million budget for the 2023-24 fiscal year, a plan that earmarks significant funds for major park infrastructure...
Mokena Park District.logo.graphic.5

Mokena Park District Overhauls Safety Policies, Adopts Cyber Attack Response Plan

In a move to bolster security and protect participants, the Mokena Community Park District Board of Commissioners on Tuesday unanimously approved a sweeping update to its personnel policies, establishing new...