Mokena Approves Additional $30,000 for Concrete Pavement Patching
Village of Mokena Board of Trustees Meeting | October 27, 2025
Article Summary: The Mokena Village Board authorized an additional $30,000 for its fiscal year 2026 concrete patching program, bringing the total project cost to $127,950. The extra funds will allow contractor P.T. Ferro Construction to address more extensive cracking found at repair sites along the village’s July 4th parade route.
Pavement Patching Key Points:
-
The board approved a change order not to exceed $30,000 for the PCC Pavement Patching project.
-
The original contract with P.T. Ferro Construction was for $97,950 to repair approximately 220 square yards of concrete.
-
Additional funds were needed after discovering more extensive underlying damage at the repair locations.
The Mokena Village Board on Monday, October 27, 2025, approved spending up to an additional $30,000 on its annual concrete pavement patching program. The funds were added to an existing contract with P.T. Ferro Construction, raising the total authorized amount for the project to $127,950.
Public Works Director Dan Peloquin explained that the village had initially awarded a $97,950 contract in September to repair about 220 square yards of concrete at three locations that required emergency asphalt patches over the summer. These spots were along the route for the village’s July 4th parade.
After the initial contract was awarded, Peloquin said that upon further examination with the contractor, it became “evident that due to the underlying cracking underneath that temporary patching, that additional pavement removal would probably be likely.”
To address the more extensive damage, staff recommended using $30,000 budgeted for emergency patchwork to increase the quantity of concrete that can be replaced as part of the planned project. The board unanimously approved the change order, allowing the contractor to complete the more comprehensive repairs.
Latest News Stories
Illinois approves $1.5B transit package, funding for long-delayed projects
Supreme Court allows Trump to withhold partial SNAP payment
Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor’s proposal would hinder employment;
Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions
Mokena Fire Station 2 Slated for Bunk Room Renovations
Mokena Enacts New Regulations for E-Bikes, Scooters, and Golf Carts
Commission Approves Mokena-Area Garage Variance Over Village’s Objection
Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements
JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit
JJC Advances ERP Modernization with New Vendor and Two-Year Budget
Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health
Congressional Perks: Committees, caucuses cost $50 million since 2019