Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Spread the love

Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Events

No events

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Briefs: Library Board of Trustees for June 24, 2025

The Library Board of Trustees unanimously approved its annual working budget after amending the family programs line to $25,000. The board is also moving forward with long-term financial planning, having...
Meeting-Briefs

Meeting Summary: Joliet Junior College Board of Trustees for June 25, 2025

The Joliet Junior College Board of Trustees met on Wednesday, June 25, 2025. Key actions included the approval of the fiscal year 2026 budget after a contentious debate and hearing...
Mokena Logo Graphic.5

Mokena Enacts Local Grocery Tax to Avert $850,000 Revenue Loss

The Mokena Village Board has moved to preserve a crucial revenue stream, unanimously approving a new local grocery tax to replace state-collected funds that will disappear in 2026. The move...
Mokena Logo Graphic.6

Mokena Dissolves Two Committees to Streamline Development Process

In a bid to become more business-friendly, the Village of Mokena is dissolving two of its long-standing advisory committees to accelerate the process for new development. Mayor George J. Metanias...
Mokena Police Logo Graphic

Mokena Police to Get New Axon In-Car Cameras in $176K Deal

The Mokena Police Department is set to receive a significant technology upgrade after the Village Board approved a five-year, $176,526 contract with Axon Enterprise for a new in-car video system....
Callery Pear trees

Mokena Targets Invasive Callery Pear Trees for Removal

The Village of Mokena is taking proactive steps to improve its urban forest by removing dozens of invasive Callery Pear trees from public parkways, funded in part by a grant...
Meeting-Briefs

Meeting Briefs: Mokena Village Board for June 23, 2025

The Mokena Village Board took several major actions at its June 23 meeting, including approving a new local grocery tax to head off a projected $850,000 revenue loss after the...
mokena school district 159.4

Mokena 159 Board Approves Amended Budget Amid Transparency, Deficit Concerns

The Mokena School District 159 Board of Education approved an amended budget for fiscal year 2025 in a contentious 6-1 vote Wednesday night, following sharp criticism from a board member...
mokena school district 159.3

Mokena 159 Board Signals Support for Recording Meetings After Public Push

Following requests from several residents, the Mokena School District 159 Board of Education on Wednesday discussed and expressed broad support for recording and publicly posting its meetings to increase transparency....
Wayfinder

District 159 Adopts ‘Wayfinder’ Program to Boost Middle Schoolers’ Social-Emotional Health

Mokena Junior High School students will have a new curriculum focused on social-emotional learning (SEL) next year after the Board of Education unanimously approved the adoption of the "Wayfinder" program....
mokena school district 159.3

Mokena 159 Principals Report End-of-Year Academic Progress, Focus on Writing

Principals from Mokena School District 159 presented their end-of-year School Improvement Plan (SIP) updates to the Board of Education on Wednesday, highlighting student progress with a particular focus on improving...
Meeting-Briefs

Meeting Briefs: Mokena School District 159 for June 18, 2025

The Mokena School District 159 Board of Education met on June 18, 2025. The board approved an amended budget for the upcoming fiscal year after significant debate. It also signaled...
Will-County-Board-Meeting-June-18-2025

Will County Board Halts Transportation Plan After Contentious 143rd Street Debate

The Will County Board voted Wednesday to send its five-year, multi-million dollar transportation improvement plan back to committee, effectively pausing all projects after a lengthy and heated debate over the...
Will-County-Board-Meeting-June-18-2025

Will County Board Upholds Zoning Denials, Rejecting Developer Appeals

The Will County Board on Wednesday backed its Planning and Zoning Commission (PZC), denying two separate appeals from property owners who sought to overturn the commission’s recommendations against their projects....
Will-County-Board-Meeting-June-18-2025

Split Vote Halts Monee Truck Terminal Project

A proposed truck terminal on vacant land at West Monee-Manhattan Road in Monee Township was stopped in its tracks Wednesday after the Will County Board delivered a split decision on...