Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Spread the love

Will County Land Use & Development Committee Meeting | March 5, 2026

Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized zoning cases, giving developers in Peotone, Joliet, Wilmington, and Monee more time to navigate federal tax policy changes and secure final building permits.

Zoning Extension Key Points:

  • Trajectory Energy Partners received a third extension for a Peotone solar farm (SEXT-26-001) due to delays caused by recent federal renewable tax credit changes.

  • Alexander Norbertus Kuypers received a second extension (SEXT-26-002) for a Peotone construction sales business, passing in a 5-1 split vote.

  • Four solar projects in Joliet and Monee townships managed by Madison Energy and Nexamp received extensions as they finalize state and local permits.

The Will County Land Use and Development Committee on Thursday, March 5, 2026, cleared a backlog of administrative hurdles, approving extensions for seven major zoning projects that have been stalled by federal red tape and interagency permitting delays.

The most heavily discussed extension involved SEXT-26-001, a third extension request for Prairie Solar LLC (Trajectory Energy Partners) regarding a previously approved solar farm on West Kennedy Road in Peotone Township.

Matt Kapinsky, representing Trajectory Energy, explained that the project was derailed by recent sweeping changes to federal renewable energy tax policies.

“The federal tax credits that have been in place for a very long time were repealed and they were set under sort of a phase-out schedule,” Kapinsky explained. “It took, after that passage, some time for just about every financing party in the entire country to get comfortable with how that was going to shake out in terms of when they were going to be eligible, how they were going to potentially procure equipment, and get equipment safe-harbored.”

The committee unanimously granted the 180-day extension, extending the special use permit through August 8, 2026.

The committee also reviewed SEXT-26-002, a second extension for Alexander Norbertus Kuypers to operate a construction sales and services business at 11233 W. Kennedy Road in Peotone. Staff noted the applicant is merely waiting on the Illinois Department of Transportation (IDOT) to issue a final site development permit.

While the extension passed 5-1, Board Member Judy Ogalla voted against it. “Just the proximity of this to residential areas… there’s three or four houses right there. Because of that, I’m going to be a no,” Ogalla stated.

The committee subsequently issued unanimous extensions for the following five solar energy facilities:

  • SEXT-26-003: A first extension for New Energy Equity (Wild Cat Solar 3) at State Route 53 and S. 216th Avenue in Wilmington.

  • SEXT-26-004: A second extension for Madison Energy (formerly Dart Farms) at Cherry Hill Road and US 52 in Joliet Township.

  • SEXT-26-005: A second extension for Madison Energy at Cherry Hill Road and W. Schweitzer Road in Joliet Township.

  • SEXT-26-006: A first extension for Nexamp (formerly Dralle Sun LLC) on the north side of Dralle Road, west of I-57 in Monee Township.

  • SEXT-26-007: A first extension for Nexamp (formerly Dralle Sun 2 LLC) southeast of S. Ridgeland Avenue and West Dralle Road in Monee Township.

Representatives for both Madison Energy and Nexamp confirmed they have executed agreements with the Will-South Cook Soil & Water Conservation District to ensure native, pollinator-friendly plantings are installed at their respective sites.

Today Jun 3
Mostly Sunny
86° 66°

Mostly Sunny

💨 10 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

County Board Approves 2026-2031 Transportation Plan Despite Project Opposition

Will County board members approved a contested five-year transportation improvement plan Tuesday after heated debate over a controversial Homer Glen road project that has drawn sustained community opposition. The Will...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Contentious I-3 Rezoning for DuPage Township Storage Yard Narrowly Advances

A proposal to rezone a 20-acre parcel in DuPage Township from agricultural to the county's most intensive industrial classification narrowly earned a recommendation for approval from the Will County Planning...
Meeting-Briefs

Will County Legislative Committee July 1 Meeting Briefs

Federal Budget Impact: Will County could face significant funding challenges if federal budget reconciliation measures reduce Medicaid and SNAP benefits. The county health department and social services rely heavily on...
Will-County-Finance-Committee-Meeting-July-1-2025

County Moves Forward with $200.8 Million Bond Refinancing Plan

Will County Finance Committee members on July 1 approved moving forward with a comprehensive bond refinancing ordinance that could save taxpayers more than $716,000 over the life of the bonds...
Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...
new-lenox-fire-district-stations.3

New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community

NEW LENOX – The New Lenox Fire Protection District is adding a four-legged member to its team after the Board of Trustees unanimously approved the creation of a new comfort...