Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Spread the love

Will County Land Use & Development Committee Meeting | March 5, 2026

Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized zoning cases, giving developers in Peotone, Joliet, Wilmington, and Monee more time to navigate federal tax policy changes and secure final building permits.

Zoning Extension Key Points:

  • Trajectory Energy Partners received a third extension for a Peotone solar farm (SEXT-26-001) due to delays caused by recent federal renewable tax credit changes.

  • Alexander Norbertus Kuypers received a second extension (SEXT-26-002) for a Peotone construction sales business, passing in a 5-1 split vote.

  • Four solar projects in Joliet and Monee townships managed by Madison Energy and Nexamp received extensions as they finalize state and local permits.

The Will County Land Use and Development Committee on Thursday, March 5, 2026, cleared a backlog of administrative hurdles, approving extensions for seven major zoning projects that have been stalled by federal red tape and interagency permitting delays.

The most heavily discussed extension involved SEXT-26-001, a third extension request for Prairie Solar LLC (Trajectory Energy Partners) regarding a previously approved solar farm on West Kennedy Road in Peotone Township.

Matt Kapinsky, representing Trajectory Energy, explained that the project was derailed by recent sweeping changes to federal renewable energy tax policies.

“The federal tax credits that have been in place for a very long time were repealed and they were set under sort of a phase-out schedule,” Kapinsky explained. “It took, after that passage, some time for just about every financing party in the entire country to get comfortable with how that was going to shake out in terms of when they were going to be eligible, how they were going to potentially procure equipment, and get equipment safe-harbored.”

The committee unanimously granted the 180-day extension, extending the special use permit through August 8, 2026.

The committee also reviewed SEXT-26-002, a second extension for Alexander Norbertus Kuypers to operate a construction sales and services business at 11233 W. Kennedy Road in Peotone. Staff noted the applicant is merely waiting on the Illinois Department of Transportation (IDOT) to issue a final site development permit.

While the extension passed 5-1, Board Member Judy Ogalla voted against it. “Just the proximity of this to residential areas… there’s three or four houses right there. Because of that, I’m going to be a no,” Ogalla stated.

The committee subsequently issued unanimous extensions for the following five solar energy facilities:

  • SEXT-26-003: A first extension for New Energy Equity (Wild Cat Solar 3) at State Route 53 and S. 216th Avenue in Wilmington.

  • SEXT-26-004: A second extension for Madison Energy (formerly Dart Farms) at Cherry Hill Road and US 52 in Joliet Township.

  • SEXT-26-005: A second extension for Madison Energy at Cherry Hill Road and W. Schweitzer Road in Joliet Township.

  • SEXT-26-006: A first extension for Nexamp (formerly Dralle Sun LLC) on the north side of Dralle Road, west of I-57 in Monee Township.

  • SEXT-26-007: A first extension for Nexamp (formerly Dralle Sun 2 LLC) southeast of S. Ridgeland Avenue and West Dralle Road in Monee Township.

Representatives for both Madison Energy and Nexamp confirmed they have executed agreements with the Will-South Cook Soil & Water Conservation District to ensure native, pollinator-friendly plantings are installed at their respective sites.

Today Jun 3
Mostly Sunny
86° 66°

Mostly Sunny

💨 10 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

new-lenox-library.2-1

Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs

NEW LENOX – The New Lenox Public Library’s creative hub, The Studio, is experiencing a surge in popularity, shattering attendance records and successfully launching new technology-driven programs, according to a...
New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
Mokena Park District.logo.graphic.1

Mokena Park District Approves $550,000 Fund Transfer for Major Park Projects

The Mokena Community Park District Board of Commissioners has approved a $550,000 fund transfer to complete several key capital projects, including the construction of a new bathroom facility at Hecht...
LWSRA

Mokena Park District Joins Regional Partners in Renewed Funding Commitment for LWSRA

The Mokena Community Park District is renewing its financial commitment to the Lincolnway Special Recreation Association (LWSRA), joining eight other local park districts in an intergovernmental agreement that ensures continued...
mokena park Yunker Barn

Mokena Park District Seeks Nearly $1 Million State Grant for Yunker Barn Renovation

The Mokena Park District is seeking nearly $1 million in state funding to help transform the historic Yunker Park Barn into a year-round facility. Executive Director Greg Vitale announced at...
Meeting-Briefs

Meeting Briefs: Mokena Park District Board of Commissioners for June 27, 2023

The Mokena Park District Board of Commissioners met on June 27 to approve funding for capital projects, renew a regional partnership agreement, and review staff reports on recent and upcoming...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
mokena library logo graphic.4

Library Board Approves Annual Budget, Begins Review of Financial Advisor Proposals

The Library Board of Trustees unanimously approved its working budget for the new fiscal year at its June 24 meeting and formally began the process of selecting a financial advisor...
Screenshot-2025-07-06-at-9.50.39-AM

Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position

Lincoln Way Community High School District 210 board members unanimously approved an amended fiscal year 2025 budget Thursday night that increases the district's operating surplus to $2.1 million while maintaining...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Screenshot-2025-07-06-at-9.45.35-AM

District 210 Approves Administrative Restructuring, Staff Salary Increases

Lincoln Way Community High School District 210 board members approved administrative restructuring and salary increases for non-union clerical support staff during closed session actions Thursday night. The board unanimously approved...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet-Junior-college.-Graphic-Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...
Meeting-Briefs

L-W School Board June 26 Meeting Briefs

Special Education District Update: The fence installation around the playground at Lincoln Way Area Special Education District 843 has been completed except for one gate section that will allow equipment...
mokena library logo graphic.10

Library Explores New IT and Copier Services Amid Equipment Failures

The Library is evaluating an overhaul of its technology services, exploring new providers for both IT support and its public-facing print management system due to ongoing equipment failures. During Tuesday's...